Celebrating 10 Years Of Advocacy: TransitMatters Exposes MBTA’s Nearly $7M Mistake With Auburndale Station

For the next five weeks, we will be highlighting landmark moments in our history so far. Next up: Our exposure of the T’s nearly $7 million mistake with Auburndale Station.

Photo credit: “Auburndale station (MBTA)” Wikipedia page

All of Newton’s Commuter Rail stations—Auburndale, West Newton, and Newtonville—currently only have single-side, low platforms. Before the 1960s, Auburndale had a station designed by H.H. Richardson and landscaped by Frederick Law Olmsted (pictured right). In 1961, the state demolished the station and two out of four tracks for the MassPike extension into Boston. On top of being inaccessible, having a platform on just one side of the tracks means it is not possible to serve passengers in both directions throughout the day. For years, the Commuter Rail has neglected riders by leaving large gaps in service to Newton.

Responding to advocacy for an accessible Commuter Rail station in Newton from residents and Representative Kay Khan, the MBTA began redesigning Auburndale Station in the late 2000s. The T initially redesigned the station with mini-high platforms due to wide freight rights, but this did not impress the community. The T went back to the drawing board, and nothing public-facing happened with Auburndale Station for about five years.

Then in 2016, there were rumors that the MBTA would finally do something with the station. In February 2017, the T presented the final Auburndale Station design to the community. The T's new plan continued to have just one platform, but now on the opposite track. However, the T didn't plan to move other single-platform stations in Newton to the opposite track. Consequently, the MBTA planned to spend 58% of the total project cost on new switching equipment for trains to swap tracks between stations. To make matters worse, the T failed to confirm whether it was possible to maintain the Framingham/Worcester Line's schedule with trains swapping tracks in Newton.

Photo credit: Miles in Transit

The T was not only about to continue neglecting Newton riders, it was about to degrade service for riders on the entire Framingham/Worcester Line. Two TransitMatters members called attention to this issue at a public meeting for the final design. The T said it hadn't checked with railroad ops.

After a few months of TransitMatters raising the alarm about Auburndale, then-Secretary of Transportation Stephanie Pollack scrapped the design and sent the MBTA back to the drawing board in May 2017.

In 2019, the T revealed their new plan to build accessible platforms on the opposite track at all three Newton Commuter Rail stations and expected the final design in the spring of 2022. The MBTA's newest design would still cause large gaps in service Commuter Rail for Newton. However, in 2021, the T changed course and committed to building two-platform, accessible stations at all three Newton Commuter Rail stations!

The MBTA's Accessibility Initiatives report from June 2023 reported that Auburndale, West Newton, and Newtonville Stations are approaching 75% design. According to this report, the MBTA should complete the final design by February 2024. However, the MBTA has still not identified a source of funding for constructing the stations. The T will not be able to afford three full station rebuilds under the current capital funding constraints. This is one of the many reasons why the T needs more funding and a dedicated funding source.

Banner Photo Credit: Leslie Anderson/THE BOSTON GLOBE